When rain left Jammu without power, it took many hands to bring it back on
Restoring power across Jammu province just days after it was disrupted due to heavy rain and floods was made possible due to multiple agencies working in tandem, officials said. The 900-MW Baglihar hydroelectric project resumed power generation 60 hours after it was shut down following the accumulation of “dangerously high levels of silt” in the Chenab, with officials attributing its restoration to round-the-clock work. They also pointed to the use of high-strength cranes to string conductors on transmission towers, and the replacement of collapsed towers with emergency restoration systems (ERS)